AMRUT

  • 90 Packages - Rs. 3223.94 Cr
  • 83 Packages Awarded  and in progress-  Rs. 3009.85 Cr (93.36%)
  • 01 Under Litigation (Kota Sewerage) - Rs. 95.19 Cr (2.95%)  (Next hearing date : 11.02.2019)
  • 03 projects under Bidding :    Rs. 7.5 Cr(0.16%)

                1.Green Space – Baran – 2.50 Cr, (Tech. Bid Opened on 18.01.2019, under Tech. Bid Evaluation , single bidder –  M/s Baba Sitanath Co.-OP LNC Society Ltd, Haryana;)

                2.Green Space- Bundi- Rs. 2.50 Cr, (Tech. Bid Opening date : 11.02.2019)

                3.Green Space- Sri Ganganagar- Rs. 2.50 Cr, (Tech. Bid Opening date : 14.02.2019)

  • 03 Bids to be re-issued:    Rs. 111.40 Cr    (3.46%)

            1.Jaipur Rehabilitation of existing Sewer line inside walled city by Trenchless Method- Rs. 74.95 Cr,

            2. Upgradation of Jaipur Delawas STP Unit- I - Rs. 33.95 Cr

            3.Green Space- Jodhpur- Rs. 2.50 Cr

S. N.

Sector

Projects approved in SAAP I, II & III

Projects approved in1st to 14th SLTC meetings

Present Status

(All projects are likely to be completed by Mar, 2020)

No. of Projects

Amount

No. of Cities covered

No. of Packages

Approved Project Cost

1

Water Supply

30

1007.36

23

23

973.32

•       23 works  are in progress (Work Order- Rs. 853.89 Cr; cost of IMIS- Rs. 33.65 Cr; Road repairing- Rs. 85.78 Cr; Total Cost- Rs. 973.32 Cr.). Financial progress: Rs. 283.06 cr.

2

Sewerage & Septage

34

2107.75

27

33

2147.54

•        30 works are in progress (Rs. 1943.45 Cr.)

•        1 work (Kota through RUIDP) under litigation  (Rs. 95.19 Cr.)

•       2 works of Rs. Rs. 108.90 Cr, bids to be reissued (Jaipur Rehabilitation of existing Sewer line inside walled city -  Rs. 74.95 Cr, Jaipur Up-gradation of Jaipur Delawas STP Unit-I Rs. 33.95 Cr.)

  Financial progress: Rs. 619.47 Cr.

3

Drainage

5

29.83

5

5

42.3

•        5 works are in progress (Rs. 42.3 Cr.)

 Financial progress: Rs. 16.30 cr.

4

Green Space & Park

81

79.00

29

29

60.78

•       25 works are  in progress(Rs. 50.78 Cr.)

•       3 works (Bundi, Sriganganagar, Baran) under bidding (Rs. 2.5 Cr each)

•       1 bid to be re- issued (Rs. 2.50 Cr. ) – Jodhpur

  Financial progress:  Rs. 11.63 cr.

 

Total

150

3223.94

29 Cities

90

3223.94

•       83 works are in progress (Rs. 3009.85 Cr., 93.36%)

•       1 work under litigation  (Rs. 95.19 Cr., 2.95%)

•       3 works under bidding( Rs. 7.5 Cr, 0.23%)

•       3 works NIT to be reissued(Rs.111.40 Cr., 3.46%)

  Financial progress: Rs. 930.46 Cr. (28.86 %)