ROB

  • 57 ROBs/RUBs have been taken up in urban area in last 5 years with project cost of Rs. 1686.86 Cr. (State share is Rs. 1049.22 Cr. and Railway share is Rs. 637.62 Cr.)
  • 36 Completed (24 ROBs & 12 RUBs) :-

               ROBs (24) : Kota(2), Jodhpur(2), Sriganganagar(1), Bikaner(2),               Chittorgarh(1), Sangaria(1), Alwar(4), Barmer(1), Makrana(1),               Nawan(1), Jaipur(2), Reengus(1), Bharatpur(1), Suratgarh(1),                Ajmer(1),         Hindaun (1), Neem ka thana (1 ROB).

              RUBs (12) :  Chomu(1), RaiSinghNagar  (1), SriKaranpur(1), Jaipur(2), Suratgarh(1), Jodhpur (2), Srigangangar(3), Chittorgarh(1).

  • 8 in progress (6 ROBs & 2 RUBs) :-

          ROBs (6) :  Kishangarh(1), Ajmer(2), Abu Road(1), Pindwara(1), Falna(1).

          RUBs  (2) : Sadul-Shahar(2) by ULB.

  • 2 ROBs Work order given : Rani & Ajmer
  • 7 yet to be started (4 ROBs & 3 RUB)

          ROBs (4) :Bikaner, Jhunjhunu, Hindaun, Gangapurcity.

          RUBs (3) : Rajgarh, Nagaur, Sangaria

  • 4 ROBs deferred by RTIDF Steering committee on 07.09.2018 : Baran, Phulera, Hanumangarh & Nimbaheda(RUB)

 

ROBs/RUBs Completed (36 Nos)                                                                 

(Amount in Lacs)

S.No

Location ROB/RUB

Executing Agency

Status/Issue

Total Cost  (Amt. in Lacs)

Actual date of completion

1.

Kota LC-15

(Bundi Road)

UIT Kota

Completed

5275.00

Aug. 13

2.

Kota LC-108 (ROB)

(Mala phatak)

IRCON

Completed

3452.00

Dec. 13

3.

Jodhpur LC-71B  (RUB)

(Khatarnakh puliya)

IRCON

Completed

951.00

Sep.13

4.

Jodhpur LC-72B

(Riktiya Bhairoji )(ROB)

JoDA

Completed

11100.00

May. 2018

5.

Jodhpur LC-165 (Saran nagar)

(ROB)

RUDF

Completed

7374.20

June. 2018

6.

Jodhpur LC-2 (RUB) (Paota)

IRCON

Completed

1340.00

March.14

7.

SriGanganagar  LC-116 (RUB)

(Near Govt. College)

UIT SriGanganagar

Completed

446.00

Nov. 13

8.

SriGanganagar  LC-118

(Near Gangasing Chowk)

Municipal Council Srigaganagar

Completed

214.14

June. 13

9.

SriGanganagar    LC-122 (RUB)

(Near Gang Cannal)

PWD

Completed

180.00

June. 15

10.

Sri Ganganagar LC-121

(Agriculture College) (ROB &  RUB)

IRCON

Completed

6678.00

ROB completed in Sept. 17 & RUB in Nov17

11.

Bikaner LC-139 (ROB)

(Chokhunti)

IRCON

Completed

2295.00

March .14

12.

Bikaner LC-4 (ROB)

(Pugal road)

RIDCOR

Completed

5094.26

Oct. 15

13.

Chittorgarh LC-88B (ROB)

(Kumbha Nagar)

IRCON

Completed

1658.00

May .14

14.

Chittorgarh  (Chanderiya) RUB

RUIDP

Completed

560.00

Dec. 15

15.

Sangaria LC-51

RIDCOR

Completed

2375.00

March .14

16.

Alwar No LC

(Arts College)

RIDCOR

Completed

2263.00

Dec. 14

17.

Alwar LC-115A

(Near Bhagar Sing Circle)

RUIDP

Completed

2500.00

Jan.15

18.

Alwar LC-116

(Near railway station)

IRCON

Completed

2530.00

June. 16

19.

Alwar LC-113 (ROB)

(Mathura phatak bye-pass)

IRCON

Completed

3452.00

July,17

20.

Barmer LC-323(A)

RUIDP

Completed

2556.09

Jan. 14

21.

Makrana  LC-34/E2

(Near Manglana)

IRCON

Completed

1771.00

10.02.16

22.

Nawan (Nagaur)  LC-21

Railway

Completed

2000.00

Jan 17

23.

Jaipur (RUB) LC-82 (Arjun nagar)

Railway

Completed

1035.00

Dec16

24.

Jaipur LC- 89 (Dadi ka fatak)

(ROB &  RUB)

IRCON

ROB completed in May, 14 &

RUB in Nov,17

4101.86

Completed

25.

Jaipur LC-228 (khirni fatak)

(ROB &  RUB)

IRCON

Completed

3768.00

ROB completed in Jan.15 & RUB in Nov,17

26.

Jaipur (RUB) LC-83-C

( Kalyan Nagar)

Railway

Completed

1272.00

Dec 17

27.

Reengus LC-108

(Khatu shayam ji mod)

IRCON

Completed

4160.00

Feb,17

28.

Bhartpur  LC-574A(ROB)

WCR/RUIDP

Completed

1747.96

May 17

29.

Surat Garh  LC-95

(Baropol road)

(ROB &  RUB)

IRCON

Completed

3666.00

ROB completed in Oct. 15 & RUB in Oct,17

30.

Suratgarh  LC 142/8-9

 (RUB)

NWR, Bikaner

Completed

717.00

Feb 2018

31.

Hindaun LC-201

(Near railway station)

IRCON

Completed

5572.00

March 2018

32.

Chomu LC-110  

(Kaladera road)     (RUB)

IRCON

Completed

2179.78

April. 14

33.

Raisingh Nagar

 LC-36 (RUB)

PWD

Completed

190.99

Dec. 14

34.

Sri Karanpur  LC - 69

RAILWAY

Completed

50.00

March 15

ROBs completed, RUB work in progress

35.

Ajmer

LC-43 &43/1(Sri Nagar Road)

IRCON

ROB Completed, commissioned & in use.

RUB is in progress

(50% work completed)

5349.00

Oct. 16/

March,19

36.

Neem ka thana  LC-76

(Main city)

IRCON

ROB completed, commissioned & in use. RUB work is in progress

(50% work completed)

4717.00

March 2018/

Feb19

Status of Ongoing ROBs/RUBs(8)

S.N

Location

Total Cost

Railway Share

State Share

Executing Agency

Status &

Likely month of completion

1.

Kishangad   LC-32, (paratiya phatak)

(2 lane ROB & 2 lane RUB)

6600.00

3300.00

3300.00

IRCON

(60% work completed)

If land is handed over upto March19, the work shall be completed by Sep 2019.

2.

Ajmer

LC-2 (ROB)

(Near Dairy)

2723.00

1323.00

1400.00

RSRDC

(70% work completed)

6 Months from the day of handing over of last piece of land.

3.

Ajmer   LC-44 (ROB)

(Gulab Badi)

3938.00

1819.00

2119.00

RSRDCC

(5 % work completed)

June  2020

4.

Abu road LC -132  (ROB)

(near railway station)

3474.00

1324.00

2150.00

RSRDC

(20% work completed)

March 2020

5.

Pindwada

LC-104(ROB)

(Station yard)

4555.00

1205.00

3350.00

DFCC

(20% work completed)

March 2020

6.

Falna LC-81(ROB)

(Station yard)

3858.60

1766.02

2092.58

DFCC

(50% work completed).

Dec 2019

7.

Sadul Shahar LC-167 (RUB) (Bhagat singh chauk)

30.00+

50.00

0.00

30.00

Municipality

(90% work completed)

 March 2019

8.

Sadul Shahar LC- 165 (RUB) (Klayan singh marg)

32.78+

50.00

0.00

32.78

Municipality

(90% work completed)

 March 2019

Work yet to be started (06 Nos)

S.N

City/Town

Funded by

Executing Agency

Cost to be Shared by Railway

Cost to be Shared by State Govt.

Total Cost

Status

 1.

Bikaner  LC-136 (ROB)                             (Near Lalgarh Station)

RTIDF

RSRDC

3980.00

4230.00

8210.00

Bids for construction work are under evaluation.

2.

Jhunjhunu LC- 265 (ROB)

RTIDF

RSRDC

1806.00

1806.00

3612.00

Bids for construction work are under evaluation.

3.

Hindaun LC-202

(ROB)

railway station yard 

State

Approaches by RSRDCC & central portion by WCR

2013.00

2013.00

4026.00

Revised GAD under preparation.

4.

Gangapurcity                LC-179 (ROB)

railway station yard

State

-DO-

1958.00

1958.00

3916.00

5.

Rajgarh (District Alwar (RUB)          LC 142

Near Station yard

Bandikui side

State

North Western Railway

300.00

500.00

800.00

GAD approved, estimate under preparation by NWR.

6.

Nagaur

 LC 61(RUB)

(Near krishi mandi, Bikaner phatak)

State

-

0.00

380.00

380.00

GAD approved. Construction Agency to be decided. Consent from PWD is awaited.

7.

Sangaria Near

 LC-50

RTIDF

M.B Sangaria

0.00

329.00

329.00

Tender yet to invited by MB, Sangariya.

Work Order given in 2 ROBs

1.

Rani LC-75

(ROB)

Near Railway Station

STATE

DFCC

1323.00

2000.00

3323.00

Work order issued on 26.5.2016. Land acquisition (1.37 hect) is under process by DFCC)

2.

Ajmer  LC-1 Near DAV college

(ROB)

STATE

RSRDCC

1323.00

1800.00

3123.00

Work order issued by RSRDCC on 28.10.16. Hon’ble high court issued a stay against District Collector, Ajmer.