ROB

Note on ROBs/RUBs under UDH & LSGD in urban areas of Rajasthan

·               57 ROBs/RUBs have been taken up in urban area in last 7 years with project cost of Rs. 1686.86 Cr. (State share is Rs. 1049.22 Cr. and Railway share is Rs. 637.62 Cr.)

·               36 ROBs/RUBs have been completed till date.

·               9 ROBs/RUBs are under progress. (4 ROBs on DFC route)

·               Work of 8 ROBs/RUBs yet to be started.

 

i)     Work order for 2 ROBs has been given (on DFC route).

ii)    Work of 6 ROBs/RUBs is yet to be started.

·                  4 ROBs/RUBs deferred by RTIDF Steering committee on 07.09.2018

 

 

ROBs/RUBs Completed (36 Nos)

                                      (Amt in lacs)

S.No

Location ROB/RUB

Executing Agency

Status/Issue

Total Cost (Amount in Lacs)

 

Actual date of completion

 

1.     

Kota LC-15

(Bundi Road)

UIT Kota

Completed

 

5275.00

Aug. 13

2.     

Kota LC-108 (ROB)

(Mala phatak)

 

IRCON

Completed

 

3452.00

Dec. 13

3.     

Jodhpur LC-71B             (RUB)

(Khatarnakh puliya)

IRCON

Completed

951.00

Sep.13

4.     

Jodhpur LC-72B

(Riktiya Bhairoji

(ROB)

JoDA

Completed

11100.00

May. 2018

5.     

Jodhpur LC-165 (Saran nagar)

(ROB)

RUDF

 

Completed

7374.20

June. 2018

6.     

Jodhpur LC-2             (RUB) (Paota)

IRCON

Completed

1340.00

March.14

7.     

SriGanganagar

LC-116 (RUB)

(Near Govt. College)

UIT SriGanganagar

Completed

446.00

Nov. 13

8.     

SriGanganagar

LC-118

(Near Gangasing Chowk)

Municipal Council Srigaganagar

Completed

214.14

June. 13

9.     

SriGanganagar    LC-122 (RUB)

(Near Gang Cannal)

PWD

Completed

180.00

June. 15

10.   

Sri Ganganagar

 LC-121

(Agriculture College)

(ROB &  RUB)

IRCON

Completed

6678.00

ROB completed in Sept. 17 & RUB in Nov17

11.   

Bikaner LC-139 (ROB)

(Chokhunti)

IRCON

Completed

 

2295.00

March .14

12.   

Bikaner LC-4 (ROB)

(Pugal road)

RIDCOR

Completed

5094.26

Oct. 15

13.   

Chittorgarh LC-88B (ROB)

(Kumbha Nagar)

IRCON

Completed

1658.00

May .14

14.   

Chittorgarh  (Chanderiya) RUB

RUIDP

Completed

560.00

Dec. 15

 

15.   

Sangaria LC-51

RIDCOR

Completed

2375.00

March .14

16.   

Alwar No LC

(Arts College)

RIDCOR

Completed

2263.00

Dec. 14

17.   

Alwar LC-115A

(Near Bhagar Sing Circle)

RUIDP

Completed

2500.00

Jan.15

18.   

Alwar LC-116

(Near railway station)

IRCON

Completed

2530.00

June. 16

19.   

Alwar LC-113 (ROB) (Mathura phatak bye-pass)

IRCON

Completed

3452.00

July,17

20.   

Barmer LC-323(A)

RUIDP

Completed

2556.09

Jan. 14

21.   

Makrana                        LC-34/E2

(Near Manglana)

IRCON

Completed

1771.00

10.02.16

22.   

Nawan (Nagaur)

LC-21

Railway

Completed

2000.00

 

Jan 17

23.   

Jaipur (RUB) LC-82 (Arjun nagar)

Railway

Completed

1035.00

 

Dec16

24.   

Jaipur LC- 89

(Dadi ka fatak)

(ROB &  RUB)

IRCON

Completed

4101.86

ROB completed in May, 14 &

RUB in Nov,17

25.   

Jaipur LC-228

(khirni fatak)

(ROB &  RUB)

IRCON

Completed

3768.00

ROB completed in Jan.15 & RUB in Nov,17

26.   

Jaipur (RUB)

LC-83-C

( Kalyan Nagar)

Railway

 

Completed

1272.00

Dec 17

27.   

Reengus

 LC-108

(Khatu shayam ji mod)

IRCON

Completed

4160.00

Feb,17

28.   

Bhartpur

LC-574A(ROB)

WCR/RUIDP

Completed

1747.96

May 17

29.   

Surat Garh          LC-95

(Baropol road)

(ROB &  RUB)

IRCON

Completed

3666.00

ROB completed in Oct. 15 & RUB in Oct,17

30.   

Suratgarh

LC 142/8-9

 (RUB)

NWR, Bikaner

Completed

717.00

Feb 2018

31.   

Hindaun LC-201

(Near railway station)

IRCON

Completed

5572.00

March 2018

32.   

Chomu LC-110  

(Kaladera road)     (RUB)

IRCON

Completed

2179.78

April. 14

33.   

Raisingh Nagar

 LC-36 (RUB)

 

PWD

Completed

190.99

Dec. 14

34.   

Sri Karanpur              LC - 69

RAILWAY

Completed

50.00

March 15

35.   

Neem ka thana

LC-76

(Main city)

IRCON

Completed

4717.00

March 2018

 

ROBs completed, RUB work in progress

S.No

Location

 

Executing Agency

Status

Total Cost (Amount in Lacs)

Actual date of completion of ROB/ Likely date of completion of RUB

36.

Ajmer

LC-43 &43/1(Sri Nagar Road)

IRCON

ROB Completed, commissioned & in use.

RUB is in progress

(70% work completed)

5349.00

Oct. 16/

Aug,19

 

 

ROBs/RUBs in Progress (9 Nos )

          (Amt. In lacs)

S.No

Location

Funded by

Total Cost

Railway Share

State Share

Executing Agency

Status &

Likely month of completion

 

 

 

Issues

1.

Kishangarh           LC-32, (paratiya phatak)

(2 lane ROB & 2 lane RUB)

STATE

6600.00

3300.00

3300.00

IRCON

(70% work completed)

If land is handed over upto July 19, the work shall be completed by Nov 2019.

4844sqm land yet to be handed over to IRCON on one side of RE wall. Initially the land was obtained through negotiation from 81 khatedars & 56 lacs were also transferred to district administration for distribution. Out of 81, one khatedar denied to provide the land due to which revised compensation proposal has been prepared by district administration which is under approval in DLB.

2.

Ajmer   LC-44 (ROB)          (Gulab Badi)

RTIDF

5349.00

1819.00

2119.00

RSRDC

(15 % work completed)

Dec2020

-

3.

 

Ajmer

LC-2 (ROB)

(Near Dairy plant)

STATE

2744.00

1372.00

1372.00

RSRDC

(70% work completed)

4 months from the date of handing over of land.

252 sqm land is coming in the alignment of the ROB. Matter is under process with  District Administration.

4.

Abu road

 LC-132 (ROB)

(near railway station)

STATE

3474.00

1324.00

2150.00

RSRDC

(20% work completed)

Dec 2020

Acquisition is under process with District Administration, Sirohi for about 2 bigha land.

5.

Pindwada

LC-104

(ROB)

(Station yard)

STATE

4555.00

1205.00

3350.00

DFCC

(20% work completed)

March 2020

No Issue.

6.

Falna LC-81

(ROB)

(Station yard)

STATE

3858.60

1766.02

2092.58

DFCC

(50 % work completed).

March, 2020

7.

Sadul Shahar LC-167 (RUB) (Bhagat singhchauk)

State + ULB

30.00+

50.00

0.00

30.00

Municipality

(90% work completed)

Aug 2019

 

8.

Sadul Shahar LC- 165 (RUB) (Klayan singh marg)

State + ULB

32.78+

50.00

0.00

32.78

Municipality

(90% work completed)

Aug 2019

 

9.

Bikaner  LC-136 (ROB)                             (Near Lalgarh Station)

RTIDF

8210.00

3980.00

4230.00

RSRDCC

(5% work completed)

Dec 2020

 

 

 

Work yet to be started (8 Nos)

S.No.

City/Town

Funded by

Executing Agency

Cost to be Shared by Railway

Cost to be Shared by State Govt.

Total Cost

Status

1.

Jhunjhunu

LC-265 (ROB)

RTIDF

RSRDC

1806.00

1806.00

3612.00

Contractor is under mobilization.

2.

Hindaun

LC-202

(ROB)

(railway station yard) (ROB)

State

Approaches by RSRDCC & central portion by WCR

2013.00

2013.00

4026.00

Revised GAD under preparation

3.

Gangapurcity                LC-179 (ROB)

(railway station yard)             (ROB)

State

-DO-

1958.00

1958.00

3916.00

4.

Rajgarh (District Alwar (RUB)                    LC 142

Near Station yard

Bandikui side

State

North Western Railway

300.00

500.00

800.00

GAD approved, estimate under preparation by NWR.

5.

Nagaur

 LC-61(RUB)

(Near krishi mandi, Bikaner phatak)

State

-

0.00

380.00

380.00

GAD approved. Construction Agency to be decided. Consent from PWD is awaited.

6.

Sangariya RUB Near  LC-50

RTIDF

Nagarpalika, Sangariya

0.00

329.00

329.00

Tenders for consultancy work are under issuance by Nagarpalika, Sangariya.

(Work order given but work yet to be started )

7.

RaniKhurd

LC-75

Station yard (ROB)

STATE

DFCC

1323.00

2000.00

3323.00

Land acquisition (1.039 hectares) under process with DFCC.

8.

 

Ajmer   LC-1 Near DAV college

(ROB)

STATE

RSRDC

1323.00

1800.00

3123.00

Work could not be started at site due to non-availability of land. About 8728.00 Sqm land of DAV College is under litigation

                 

 

 

ROBs/RUBs deferred by RTIDF Steering Committee on 07.09.2018 (4)

  1.

Baran LC-38

(near railway station) (ROB)

RTIDF

RSRDC

2050.00

2050.00

4100.00

Proposal has been deferred by RTIDF Committee on 07.09.2018.

 

2.

Phulera

LC-01(ROB)

Near Railway Station towards Sambhar Side

RTIDF

North Western Railway

3130.00

3130.00

6260.00

3.

Hanumangarh LC-70 (ROB)              (Chuna Phatak)

RTIDF

RSRDC

3000.00                         

3000.00

6000.00

4.

Nimmbaheda

 LC-103 (RUB)

RTIDF

Western Railway

254.00

254.00

508.00