ROB

Note on ROBs/RUBs under UDH & LSGD in urban areas of Rajasthan

  • 56 ROBs/RUBs have been taken up in urban area in last 5 years with project cost of Rs. 1683.57 Cr. (State share is Rs. 1045.93 Cr. and Railway share is Rs. 637.62 Cr.)
  • 36 ROBs/RUBs have been completed till date.
  • 7 ROBs/RUBs are under progress. (4 ROBs on DFC route)
  • Work of 13 ROBs/RUBs yet to be started.

i)      Work order for 2 ROBs has been given (on DFC route).

ii)    Work of 11 ROBs/RUBs is yet to be started (7 sanctioned from RTIDF & 4 are state funded)

ROBs/RUBsCompleted (35 Nos)

                                      (Amt in lacs)

S.No

Location ROB/RUB

Executing Agency

Status/Issue

Total Cost (Amount in Lacs)

 

Actual date of completion

 

1.   

Kota 15

UIT Kota

Completed

 

5275.00

Aug. 13

2.   

Jodhpur 71B             (RUB)

IRCON

Completed

1000.00

Sep.13

3.   

SriGanganagar 116 (RUB

UIT SriGanganagar

Completed

446.00

Nov. 13

4.   

SriGanganagar C118

Municipal Council Srigaganagar

Completed

214.14

June. 13

5.   

Kota 108

IRCON

Completed

 

3051.26

Dec. 13

6.   

Bikaner 139

IRCON

Completed

 

1912.02

March .14

7.   

Chittorgarh  88B

IRCON

Completed

1749.00

May .14

8.   

Jodhpur C2             (RUB)

IRCON

Completed

1812.03

March .14

9.   

Chomu 110        (RUB)

IRCON

Completed

2021.03

April. 14

10. 

Sangaria C51

RIDCOR

Completed

2375.00

March .14

11. 

Alwar No LC (Arts College)

RIDCOR

Completed

2263.00

Dec. 14

12. 

Bikaner 4

RIDCOR

Completed

5094.26

Oct. 15

13. 

Barmer 323(A)

RUIDP

Completed

2556.09

Jan. 14

14. 

Alwar 115A

RUIDP

Completed

2500.00

Jan.15

15. 

Raisingh Nagar 36 (RUB)

PWD

Completed

190.99

Dec. 14

16. 

SriGanganagar 122 (RUB)

PWD

Completed

180.00

June. 15

17. 

Sri Karanpur              LC - 69

RAILWAY

Completed

50.00

March 15

18. 

Chittorgarh  (Chanderiya) RUB

RUIDP

Completed

560.00

Dec. 15

 

19. 

Makrana                        C-34/E2

IRCON

Completed

1933.12

10.02.16

20. 

Alwar lc 116

IRCON

Completed

2440.38

June. 16

21. 

Nawan lc 21

Railway

Completed

2000.00

 

Ja

n 17

22. 

Jaipur (RUB) 82(Arjun nagar)

 

Railway

Completed

1035.00

 

Dec16

23. 

Reengus

 Lc 108

IRCON

Completed

3959.00

Feb,17

24. 

Bhartpur.574A(ROB)

WCR/RUIDP

Completed

1747.96

May 17

25. 

Alwar 113

IRCON

Completed

2823.26

July,17

26. 

Sri Ganganagar

 LC1-121

(ROB &  RUB)

IRCON

Completed

6029.00

ROB completed in Sept. 17 & RUB in Nov17

27. 

Surat Garh          C95

(ROB &  RUB)

IRCON

Completed

3100.48

ROB completed in Oct. 15 & RUB in Oct,17

28. 

Jaipur 89

(ROB &  RUB)

IRCON

Completed

4022.86

ROB completed in May, 14 &

RUB in Nov,17

29. 

Jaipur 228

(ROB &  RUB)

IRCON

Completed

3377.48

ROB completed in Jan.15 & RUB in Nov,17

30. 

Jaipur (RUB)

LC-83-C

( Kalyan Nagar)

Railway

 

Completed

1272.00

Dec 17

31. 

Suratgarh

LC 142/8-9 (RUB)

NWR, Bikaner

Completed

717.00

Feb 2018

32. 

Hindaun LC-201

IRCON

Completed

5234.66

15,March 2018

33. 

Jodhpur LC-72B (ROB)

JoDA

Completed

11100.00

10.05.2018

34. 

Jodhpur LC-C165 Saran nagar

(ROB)

RUDF

 

Completed

7500.00

22.06.2015

ROBs completed, RUB work in progress

 

S.No

Location

 

Executing Agency

Status

Total Cost (Amount in Lacs)

Actual date of completion of ROB/ Likely date of completion of RUB

35.

Ajmer LC 43 &43/1

IRCON

ROB Completed, commissioned & in use.

RUB is in progress

(50% work completed)

3649.92

Oct. 16/

Sep,18

36.

Neem ka thana

LC-76

IRCON

ROB completed, commissioned & in use. RUB work is in progress

(10% work completed)

4700.00

20.March 2018/ Sep 2018

Issues regarding completed ROBs:-

 

1.

Kota

 LC-108      

ROB completed in 2013 but balance fund of Rs. 2.5 cr. is still to be made to executing agency for want of revised A&F from UIT Kota.

2.

Alwar

 LC-113

4.00 Cr is required from UIT Alwar for which several letters have already been written to UIT Alwar.

3.

Suratgarh LC-95  

Rs.60.00 Lacs is to be paid by ULB on account of construction of extra leg of RUB.

 

4.

Ajmer

LC-43/1

Rs. 4.50 Cr is required from ADA, Ajmer for which letters have already been written to ADA, Ajmer. It is informed by the construction agency that work will be stopped, if payment will not be made. Amount sanctioned from RUDF is Rs. 22.85 Cr., out of which only 18.49 Cr has been released so far.

 

ROBs/RUBs in Progress (4 Nos )

(Progress up to 25.06.2018)

          (Amt. In lacs)

S.No

Location

Funded by

Total Cost

Railway Share

State Share

Executing Agency

Status &

Likely month of completion

 

 

 

Issues

1.   

Sadul Shahar LC-167 (RUB) (Bhagat singhchauk)

State + ULB

30.00+

50.00

0.00

30.00

Municipality

(60% work completed)

 

 

Work stopped by contractor in Jan 2017. ULB terminated the contract & re invited bids. Meanwhile old contractor obtained stay from the court. Matter was under litigation. Now, Work order given to new contractor for remaining works in March. Work is likely to be completed by Aug18.

2.   

Sadul Shahar LC- 165 (RUB) (Klayan singh marg)

State + ULB

32.78+

50.00

0.00

32.78

Municipality

(90% work completed)

 

3.   

Kishangad           LC-32, (paratiya phatak)

(2 lane ROB & 2 lane RUB)

STATE

4548.30

1040.86

3507.44

IRCON

(45% work completed)

One side approach & central portion under construction

ii) 4844sqm land yet to be handed over to IRCON on one side of RE wall due to litigation.  Initially the land was obtained through negotiation from 81 khatedars & 56 lacs were also transferred to district administration for distribution. Out of 81, only 31 cheques issued to khatedars, 30 are residing out of station, 3 khatedars have obtained court stay, 15 have been died, 4 are not being present after notification etc. Now District Administration is in dilemma. Matter is still pending. M.O.U with state & IRCON also expires in July 2018. IRCON is not ready to further extension of M.O.U

6 ROBs on DFC Route

(Work of 4 ROBs is ongoing)

 

S. No.

Town

Funded by

Total Cost (Amt in Lacs)

Railway Share

State Share

 

Executing Agency

 

Status/

Scheduled date of completion

Issues

1

 

Ajmer

LC-2 (ROB)

(Near Dairy)

STATE

2723.00

1323.00

1400.00

RSRDC

(30% work completed)

Dec, 18

Rs 330.00 lacs released & demand is of Rs 400.00 lacs

1. 252 sqm land is coming in the alignment of the ROB. The incumbent is demanding 250 sqm land at some other place for which file is in process with ADA.

2. Work is on hold for want of funds, State Govt denied for providing further funds, until funds received from Railway.

2

 

Abu road

 LC 132 (ROB)

(near railway station)

STATE

3474.00

1324.00

2150.00

RSRDC

(15% work completed)

Sept,19

Rs 215.00 Lacs released & demand is of Rs. 150.00 lacs

1. Acquisition process has been started by District Administration for about 2 bigha land.

2.Work is on hold for want of funds & land, State Govt denied to provide further funds, until funds received from Railway.

3

Pindwada

LC-104

(ROB)

(Station yard)

 

STATE

4555.00

1205.00

3350.00

DFCC

(10% work completed)

March,19

Proposal of 20E of land acquisition (1.47 Hect) submitted for publishing Gazette notification.

4

Falna LC-81

(ROB)

(Station yard)

 

STATE

3858.60

1766.02

2092.58

DFCC

(20 % work completed).

Feb, 19

No Issue

(Work yet to be started on 2 ROBs)

5

Rani     LC-75

(ROB)

 

STATE

3323.00

1323.00

2000.00

DFCC

Work order issued on 26.5.2016

(for 20 months). GAD under approval

Notification issued for 20A of land acquisition (1.039 hectares)

6

 

Ajmer   LC-1 Near DAV college

(ROB)

STATE

3123.00

 

1323.00

 

1800.00

RSRDC

Work order issued by RSRDCC on 28.10.16     (The likely date of completion of work shall be 18 months from the date of acquisition of required land.)

Work could not be started at site due to non-availability of land. About 8728.00 Sqm land of DAV College, Ajmer is to be acquired. This land was provided on lease to DAV, now the lease has been cancelled. Land is required to be transferred to RSRDCC by ADA.

 

Work yet to be started (11 Nos)

ROBs/RUBs awarded to RSRDCC (4 nos.)


S.No.

City/Town

Funded by

Executing Agency

Cost to be Shared by Railway

Cost to be Shared by State Govt.

Total Cost

Status

Likely date of start/Completion

1.

Ajmer   LC-44 (ROB)          (Gulab Badi)

RTIDF

RSRDC

1819.00

2119.00

3938.00

GAD approved. Single bid received on 03.05.2018 which was cancelled and fresh bids are being invited.

  Sep18/

Aug 20

 

 2.

Bikaner  LC-136 (ROB)                             (Near Lalgarh Station)

RTIDF

RSRDC

3980.00

4230.00

8210.00

Modified GAD under approval from Railway & likely to be approved by June18.

Sep18/

Aug 20

 

3.

Jhunjhunu LC 265 (ROB)

RTIDF

RSRDC

1806.00

1806.00

3612.00

Modified GAD under approval from Railway & likely to be approved by June18.

Sep18/

   Aug. 20

4.

Hanumangarh LC 70 (ROB)              (Chuna Phatak)

RTIDF

RSRDC

3000.00                         

3000.00

6000.00

Modified GAD under approval from Railway & likely to be approved by June18.

Sept. 18/

   Sep 20

ROBs/RUBs awarded to Railway (4 nos.)

5.

Nimmbaheda

 LC 103 (RUB)

RTIDF

Western Railway

254.00

254.00

508.00

GAD under preparation by W.R.

Sep18/ June 19

 

6.

Phulera LC 01(ROB)

RTIDF

North Western Railway

3130.00

3130.00

6260.00

GAD & DPR under preparation by NWR. Likely to be completed by June 18

Sep18/   Sep 20

b. 18

7.

Rajgarh (District Alwar (RUB)                    LC 142

State

North Western Railway

300.00

500.00

800.00

GAD approved, estimate under preparation by NWR . Construction work is likely to be started in Aug 18

Sep18/ July.19

8.

Nagaur

 LC 61(RUB)

State

-

0.00

380.00

380.00

GAD approved. Construction Agency to be decided.

June 18/ Jan.19

 

ROBs to be constructed on double entity (3 nos. RSRDCC +WCR)

9.

Hindaun LC202

       (ROB)      

State

Approaches by RSRDCC & central portion by WCR

2013.00

2013.00

4026.00

Revised GAD under preparation & likely to be submitted to Railway by 31 May 18.

. Sep 18/ Oct. 20  18/ Feb. 20

10.

Gangapurcity                LC 179 (ROB)

State

-DO-

1958.00

1958.00

3916.00

Sep18/ Oct. 20

11.

Baran LC-38 (ROB)

RTIDF

-DO-

2050.00

2050.00

4100.00

GAD approved. DPR under preparation. NIT for construction work shall be called in next 30 days.

Sep 18/ Oct. 20