Menu

AMRUT

Status of sanctioned projects in SAAP & SLTC

S. No.

Name of Towns

Projects

Approved in SAAP

Approved in SAAP

Approved in SLTC

Status of work

1

Bhiwadi

Sewerage

SAAP-I

110.00

105.60

1st SLTC  on 30.11.2015
LoA issued  to M/s L&T vide no. 2122 dated 10.05.2016 amounting RS. 121.43 (with Provisional Sum & without O&M and SBM)
NTP issued vide no. 6126 dated 04.07.2016
Progress:-
Sewer line 31.00 Km laid out of 109 Km, STPs & Septage work is in progress.
Physical Progress- 28%
Financial Progress- 10 Crs

Water Supply

SAAP-I

20.00

17.79

3rd SLTC  on 25.04.2016
Work order issued to M/s Indian Hume Pipe Company Ltd. vide no. 5874 dated 31.03.2017 amounting Rs. 15.07 (Without O&M)
Physical Progress- 0.00% 
Financial Progress- 0.0 Crs

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.13

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

132.50

125.52

 

2

Beawar

Sewerage

SAAP-I

110.00

109.91

3rd SLTC  on 25.04.2016
LOA issued to M/s DR Agarwal-Bhugan Infra Private Ltd (JV) viden No.14431, dated 21.02.2017 amounting RS. 112.76 (with Provisional Sum & without O&M and SBM)
NTP issued vide letter no. 37 dated 06.04.2017
Progress:-
Confirmatory survey done. Land handed over to contractor. Soil testing under progress. Compound wall under progress at Vijay Nagar Pvt. Bus Stand STP. 
Physical Progress- 0.00 %
Financial Progress- 0.00 Crs

Water Supply

SAAP-I (14.00) & SAAP-II (14.53)

28.53

28.53

2nd SLTC  on 21.03.2016
NIT issued on 16.01.2017
Bids received on 21.03.2017, 4 bidders participated and Financial bid opened on last week of April'2017 & work order to be placed shortly.

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

8th SLTC on 27.01.2017
NIT issued on 20.04.2017,
Bid to be opened on 30.05.2017.

Total

 

141.03

140.94

 

3

Hanumangarh

Sewerage

SAAP-II

6.98

6.98

3rd SLTC  on 25.04.2016
LoA issued to  M/s MTS- EIEPL (JV) vide no. 2059 dated 12.10.2015 amounting Rs. 7.08 (with ProvisionalSum & without O&M).
NTP issued to vide letter no. 5091, dated 19.10.2015
Progress:-
01 No. STP work is in progress.
Physical Progress- 95% 
Financial Progress- 5.90 Crs

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

6th SLTC on 25.10.2017
NIT issued on 15.02.2017
Bid received on 16.05.2017 & I bid received.

Total

 

9.48

9.48

 

4

Gangapur City

Sewerage

SAAP-II

99.42

99.42

2nd SLTC  on 21.03.2016
LoA issued to M/s Larsen & Toubro Limited vide no. 1745 dated 21.02.2017 amounting Rs. 111.56  (with Provisional Sum & without O&M and SBM)
NTP issued vide letter No.24038, dated 24.03.2017 Progress:-
Confirmatory survey done. Office established. Soil testing under progress. SIP submitted to PDMC.
Physical Progress- 0.00 %
 Financial Progress- 0.00 Crs

Water Supply

SAAP-I (40.00) & SAAP-II (19.81)

59.81

59.81

2nd SLTC  on 21.03.2016
Re-tender to be invited

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

9th SLTC on 30.03.2017
NIT issued on- 12.04.2017
Bid to be received on- 30.05.2017

Total

 

161.73

161.73

 

5

Hindaun City

Sewerage

SAAP-II

91.64

91.64

2nd SLTC  on 21.03.2016
LoA issued to M/s Larsen & Toubro Limited vide no. 5760 dated 23.02.2017 amounting Rs. 96.76  (with Provisional Sum & without O&M and SBM)
NTP issued vide letter No.6137, dated 24.03.2017.
Progress:-
Confirmatory survey done. Soil testing under progress. SIP submitted to PDMC.
Physical Progress- 0.00 % 
Financial Progress- 0.00 Crs

Water Supply

SAAP-III

20.57

20.57

6th SLTC  on 25.10.2016
NIT issued on 20.02.2017
Bid received on 13.04.2017
Financial Bid to be opened in the first week of May and work order likely by June, 2017

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

114.71

114.71

 

6

Sujangarh

Sewerage

SAAP-II

100.00

100.00

2nd SLTC  on 21.03.2016
LOA issued to M/s YFC-ZTI (JV)  dated 22.02.2017 amounting Rs. 100.30 (with Provisional Sum & without O&M and SBM)
NTP issued vide letter no. 7026 dated 31.03.2017.
Progress:-
Land handed over to contractor. Confirmatory survey done. SIP submitted to PDMC.
Physical Progress- 0%
 Financial Progress- 0.00  Crs

Water Supply

SAAP-I

25.00

13.06

2nd SLTC  on 21.03.2016
NIT issued on 17.03.2017
Bid to be received on 25.04.2017
Tenders received and under evaluation. Work order likely in the last week of May, 2017

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.00

9th SLTC  on 30.03.2017
NIT issued on 08.05.2017.
Bid to be received on 11.06.2017.

Total

 

127.50

115.06

 

7

Bikaner

Sewerage

SAAP-III

113.58

113.58

6th SLTC  on 25.10.2016
NIT issued on 04.01.2017.
Technical bid opened on 03.04.2017 (under evaluation)

Water Supply

SAAP-III

34.95

34.95

6th SLTC on 25.10.2016
Tender to be invited

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.19

11th SLTC on 18.07.2017

NIT to be issued.

Total

 

151.03

150.72

 

8

Jodhpur

Sewerage

SAAP-I

85.00

85.00

1st SLTC  on 30.11.2015
LoA issued to M/s Laxmi Construction vide no 18263 Dated 03.10.2016 amounting Rs. 68.03 (with Provisional Sum & without O&M and SBM)
NTP issued to  vide letter no. 34514 dated 13.12.2016
Progress:-
Third Party Inspection for 250 mtrs RCC Pipe & 1 Km HDPE pipes were completed. Procuring of pipes will be started with in 2 days.
Physical Progress- 4%
 Financial Progress- 0.00  Crs

Water Supply

SAAP-III

25.00

10.16

7th SLTC on 02.12.2016
Tender to be invited

Drainage*

-

 

14.84

10 th SLTC on 17.05.2017
NIT to be issued.

Green Space

SAAP-I (1.00) & SAAP-II (0.50) & SAAP-III (1.00)

2.50

2.50

9th SLTC on 30.03.2017
NIT issued on 08.05.2017.

Total

 

112.50

112.50

 









9









Alwar

Sewerage

SAAP-I

80.00

66.97

1st SLTC  on 30.11.2015
LoA issued  to M/s L&T vide no. 2122 dated 10.05.2016 amounting RS. 70.65 (with Provisional Sum & without O&M and SBM)
NTP issued vide no. 6126 dated 04.07.2016.
Progress:-
Sewer line 26.00 Km laid out of 152.75 Km. Physical progress 15.00% completed.
Physical Progress- 15%
Financial Progress- 5.40 Crs

Water Supply

SAAP-I (50.00) & SAAP-II (40.62)

90.62

90.62

3rd SLTC  on 25.04.2016
Work order issued to M/s Indian Hume Pipe Company Ltd. vide no. 5874 dated 31.03.2017 amounting Rs. 86.80 (Without O&M)
Physical Progress- 0.00% 
Financial Progress- 0.0 Crs

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.49

8th SLTC  on 27.01.2017
NIT issued on 07.02.2017
Bid to be received on 25.05.2017

Total

 

173.12

160.08

 

10

Bharatpur

Sewerage

SAAP-II

79.66

79.66

2nd SLTC  on 21.03.2016
LoA issued to M/s L&T vide no. 12935 dated 27.02.2017 amounting Rs. 81.64 (with Provisional Sum & without O&M and SBM)
NTP issued vide no. 13949 dated 24.03.2017
Progress:-
Confirmatory survey done. SIP submitted to PDMC.
Physical Progress- 0%
 Financial Progress- 0.00  Crs

Water Supply

SAAP-III

50.00

49.58

7th SLTC  on 02.12.2016
NIT issued on 30.03.2017
Bid to be received on 23.05.2017

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

5th SLTC  on 15.09.2016
NIT issued on 11.05.2017
Bid to be received on 22.06.2017.

Total

 

132.16

131.74

 

11








Sikar

Sewerage

SAAP-I

110.00

110.08

1st SLTC  on 30.11.2015
LoA issued  to M/s L&T vide no. 2122 dated 10.05.2016 amounting RS. 99.99 (with Provisional Sum & without O&M and SBM)
NTP issued vide no. 6126 dated 04.07.2016
Progress:-
Sewer line 33.50 Km laid out of 125.90 Km, STPs work is in progress.
Physical Progress- 27%
Financial Progress- 6.00 Crs

Water Supply

SAAP-II

30.50

30.50

2nd SLTC  on 21.03.2016
Work Order issued to M/s Devender Construction Company vide letter no. 9777 dated 30.12.2016 amounting Rs. 24.28 (Without O&M)
Physical Progress- 0.00%
Financial Progress- 0.0 Crs

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

143.00

143.08

 

12

Dhaulpur

Sewerage

SAAP-III

24.00

24.00

9th SLTC  on 30.03.2017
NIT issued on 01.05.2017
Bid to be received on 23.06.2017.

Water Supply

SAAP-I (30.00) & SAAP-II (11.67)

41.67

41.67

2nd SLTC  on 21.03.2016
NIT issued on 20.02.2017
Bid received on 13.04.2017
Tender Received, Financial Bid to be opened in the second week of May, Work order likely to be placed in the last week of May, 2017

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

68.17

68.17

 

13

Sawai Madhopur

Sewerage

SAAP-III

24.00

24.00

9th SLTC  on 30.03.2017
NIT issued on 26.10.2016.
Technical Bid Opened on- 05.01.2017
Financial Bid opened on 22.02.2017
NIT issued by RUIDP.
LOA issued to M/s Gujrat Construction Company-AEC (JV) on 08.05.2017.

Water Supply

SAAP-III

50.00

48.87

5th SLTC  on 15.09.2016 (47.32 Cr)
10th SLTC on 17.05.2017 (1.55 Cr)
NIT issued on 20.02.2017
Bid received on 13.04.2017
Evaluation under process, Work order likely Last week of May, 2017

Green Space

SAAP-I

4.00

3.50

2nd SLTC  on 21.03.2016
LoA issued to M/s Padmavati Enterprises  vide letter no. 15843 dated 18.01.2017 amounting Rs. 3.26.
Work order i vide no. 21117 on 27.03.2017
Physical Progress- 0.00%
Financial Progress- 0.0 Crs

Total

 

78.00

76.37

 

14

Churu

Sewerage

SAAP-II

98.37

98.37

2nd SLTC  on 21.03.2016
LOA issued to M/s YFC-ZTI (JV) vide  No.18813, dated 02.03.2017 amounting Rs. 98.11  (with Provisional Sum & without O&M and SBM)
NTP issued vide letter no. 566 dated 20.04.2017
Progress:-
Land handed over to the contractor. Confirmatory survey done.
Physical Progress- 0%
 Financial Progress- 0.00  Crs

Water Supply

SAAP-III

20.79

20.79

6th SLTC  on 25.10.2016
NIT issued on 15.03.2017
Bid to be received on 25.04.2017
 Tenders received and under evaluation. Work order likely in the last week of May, 2017

Drainage

SAAP-III

6.33

6.33

5th SLTC on 15.09.2016
NIT issued on 30.11.2016.
Technical bid opened on 03.01.2017.
Evaluation done on 02.02.2017.
Financial bid opened on 09.02.2017.
Work Order issued amounting Rs. 6.08 Crs

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.49

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

127.99

127.98

 

15

Baran

Sewerage

SAAP-II

85.00

85.00

2nd SLTC  on 21.03.2016
LOA issued to M/s Tata Projects Ltd-M/s Jyoti Buildtech Pvt. Ltd (JV) vide letter No.8051, dated 21.02.2017 amounting Rs. 89.42 (with Provisional Sum & without O&M and SBM)
NTP issued vide no. 611 dated 26.04.2017
Progress:-
Land handed over to contractor. Confirmatory survey under progress.
Physical Progress- 0.00 %
Financial Progress- 0.00 Crs

Water Supply

SAAP-I (50.00) & SAAP-II (28.31)

78.31

78.31

3rd SLTC  on 25.04.2016
NIT issued on 27.01.2017
Bid received on 15.03.2017
 2 bids received. Technical Evaluation Completed, Financial Bid to be opened on 05/05/2017 and work order to be placed by Mid of May, 2017

Drainage

SAAP-III

1.00

1.00

7th SLTC on 02.12.2016
NIT issued on 22.12.2016
Technical bid opened on 23.01.2017.
Evaluation done on 20.02.2017. Financial bid opened on 05.04.2017.
Work Order issued amounting Rs. 1.01 Crs

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

5th SLTC  on 15.09.2016
NIT issued on 11.04.2017
Bid to be received on 22.05.2017

Total

 

166.81

166.81

 

16

Chittorgarh

Sewerage

SAAP-II

87.89

87.89

3rd SLTC  on 25.04.2016
LoA issued to  M/s Tata Projects Ltd-M/s Jyoti Buildtech Pvt. Ltd (JV) vide no. 12290-12303 dated 21.02.2017 amounting Rs. 103.36 (With Provisional Sum & Without O&M and SBM)
 NTP issued vide no. 114- 132 dated 17.04.2017.
Progress:-
Office established. Confirmatory survey under progress.
Physical Progress- 0% 
Financial Progress- 0 Crs

Water Supply

SAAP-I (40.00) & SAAP-III (15.00)

55.00

55.00

6th SLTC on 25.10.2017
Tender to be invited

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

6th SLTC on 25.10.2017
NIT issued on 05.05.2017.
Bid to be opened on 14.06.2017

Total

 

145.39

145.39

 

17

Nagaur

Sewerage

SAAP-I

60.00

60.02

2nd SLTC  on 21.03.2016
LOA issued  to M/s YFC Projects Pvt. Ltd-ZTI (JV) vide letter No.1398, dated 20.02.2017 amounting Rs. 58.99 (with Provisional Sum & without O&M and SBM)
NTP issued vide letter no. 62 dated 17.04.2017
Progress:-
Confirmatory survey done. Land handed over to contractor. Soil testing under progress.
Physical Progress- 0%
Financial Progress- 0.00  Crs

Water Supply

SAAP-I

50.00

50.06

3rd SLTC  on 25.04.2016
NIT issued on 16.01.2017
Bids received on 21.03.2017, 5 bidders participated and Financial bid opened on last week of April'2017 & work order to be placed shortly.

Green Space

SAAP-I (0.50) & SAAP-II (2.00)

2.50

2.50

2nd SLTC on 21.03.2016
NIT issued on 17.04.2017,
Bid to be received on 25.05.2017

Total

 

112.50

112.58

 

18

Bundi

Sewerage

SAAP-II (52.29) & SAAP-III (47.71)

100.00

100.00

3rd SLTC  on 25.04.2016
LoA issued to M/s Tata Projects Ltd-M/s Jyoti Buildtech Pvt. Ltd (JV) vide no. 9913 dated 22.02.2017 amounting Rs. 102.62 (with Provisional Sum & without O&M and SBM)
NTP issued vide no. 478 dated 26.04.2017
Progress:-
Land handed over to contractor. Confirmatory survey done.
Physical Progress- 0.00 % 
Financial Progress- 0.00 Crs

Water Supply

SAAP-II

46.36

46.36

3rd SLTC  on 25.04.2016
NIT issued on 27.01.2017
Bid received on 15.03.2017
4 bids received. Technical Evaluation Completed, Financial Bid to be opened on 05/05/2017 and work order to be placed by Mid of May, 2017

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

5th SLTC  on 19.09.2016
NIT issued on 12.04.2017
Bid to be received on 17.05.2017.
Revised date of bid receivng on…………..

Total

 

148.86

148.86

 

19

Bhilwara

Sewerage

SAAP-III

10.00

9.95

9th SLTC  on 30.03.2017
NIT issued on 06.10.2016
Technical Evaluation done- 22.03.2017.
Financial Bid Opened on- 28.03.2017 (under Evaluation)
NIT issued by RUIDP.

Water Supply

SAAP-I

25.00

23.33

2nd SLTC  on 21.03.2016
NIT issued on 16.01.2017
Bids received on 21.03.2017, 5 bidders participated and Financial bid opened on last week of April'2017 & work order to be placed shortly.

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

5th SLTC  on 15.09.2016
NIT issued on 05.05.2017.
Bid to be received on 12.06.2017.

Total

 

37.50

35.78

 

20

Sriganga Nagar

Sewerage

SAAP-III

10.00

10.00

9th SLTC  on 30.03.2017
NIT issued on - 03.02.2016
Technical Evaluation done- 23.08.2016
Finacial Evaluation done- 26.08.2016
Work order issued by RUIDP
NTP issued by RUIDP to M/s Larsen & Turbo Ltd. Work is in progress.(SIP under scrutiny, HDPE & PVC pipe procured.

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

6th SLTC on 25.10.2017
NIT issued on 24.03.2017
bid received on 10.05.2017.
No bid received.
Re tender to be issued

Total

 

12.50

12.50

 

21

Pali

Sewerage

SAAP-III

10.00

10.00

9th SLTC  on 30.03.2017
NIT issued- 24.04.2015
Technical evaluation done- 24.08.2015
Financial Evaluation done- 26.08.2015
Work awarded - M/s L&T
Work order issued by RUIDP
 Work is in progress (Physical- 28.11 %).

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.18

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

12.50

12.18

 

22

Tonk

Sewerage

SAAP-III

10.00

10.00

9th SLTC  on 30.03.2017
NIT issued- 24.03.2015
Technical evaluation done- 10.08.2015
Financial evaluation done- 11.08.2015
Work order issued by RUIDP
NTP issued by RUIDP to M/s Tonk Water Supply Ltd. Vide no. 52 dated 30.11.2015. work is in progress (Physical- 10.30 %).

Green Space

SAAP-I (0.50) & SAAP-II (4.50)

5.00

5.00

2nd SLTC  on 21.03.2016
NIT issued on 30.01.2017
Bid received on 28.03.2017, 3 bids received (under evaluation, 3 bidder participated)

Total

 

15.00

15.00

 

23

Jhunjhunu

Drainage

SAAP-III

11.00

11.00

9th SLTC  on 30.03.2017
NIT issued on 16.05.2017.
Bid to be received on 03.07.2017

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

5th SLTC  on 15.09.2016
NIT issued on 04.05.2017.
Bid to be received on 13.06.2017

Total

 

13.50

13.50

 

24

Kishangarh

Sewerage

SAAP-III

100.29

100.29

5th SLTC  on 15.09.2016
LOA issued to M/s DR Agarwal-Bhugan Infra Private Ltd (JV) vide letter No.1348, dated 23.02.2017 amounting Rs. 105.30 (with Provisional Sum & without O&M and SBM
NTP issued vide no. 1480A dated 03.04.2017
Progress:-
Confirmatory survey under progress.
Physical Progress- 0%
 Financial Progress- 0.00  Crs)

Green Space

SAAP-I (0.50), SAAP-II (0.50) & SAAP-III (1.50)

2.50

2.50

5th SLTC  on 15.09.2016
NIT issued on 03.03.2017
bid received  on 07.04.2017, 1 bidder praticipated (under evaluation). 
NIT re issued on 05.05.2017.
Bid to be received on 08.06.2017

Total

 

102.79

102.79

 

25

Jaipur

Sewerage

SAAP-III

171.52

49.14+5.82+25=79.96

6th SLTC  on 25.10.2016
NIT published on 02.05.2017, bid to be received on 16.06.2017 for Brahmapuri STP, Talkatora STP & Walled City tender to be reinvited.

Water Supply

SAAP-III

50.00

50.00

8th SLTC on 27.01.2017
Tender to be invited

Green Space

SAAP-I (1.00), SAAP-II (0.50) & SAAP-III (1.00)

2.50

2.50

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

224.02

129.96

 

26

Kota

Sewerage

SAAP-III

102.19

95.19

9th SLTC  on 30.03.2017.
NIT issued on 30.01.2017
Bids to be opened on 18.05.2017.
NIT issued by RUIDP.

Water Supply

SAAP-II (60.25) & SAAP-III (10.00)

70.25

60.25+10.00=70.25

3rd SLTC on 25.04.2017 & 6th SLTC on 25.10.2016
Tender to be invited

Green Space

SAAP-I (1.00), SAAP-II (0.50) & SAAP-III (1.00)

2.50

2.50

6th SLTC on 25.10.2017
NIT issued on 15.03.2017
bid received on 17.04.2017, 3 bids received (Under evealuation, 3 bidder praticipated).

Total

 

174.94

170.44

 

27

Ajmer

Sewerage

SAAP-III

68.21

68.21

5th SLTC  on 15.09.2016
LOA issued to DR Agarwal-Bhugan Infra Private Ltd (JV) vide letter No.3106, dated 02.03.2017 amounting Rs. 68.53 (with Provisional Sum & without O&M and SBM)
NTP isseued vide no. 3569-89 dated 31.03.2017
Progress:-
Confirmatory survey under progress.
Physical Progress- 0%
Financial Progress- 0.00  Crs

Water Supply

SAAP-III

30.00

29.98

9th SLTC on 30.03.2017
Tender to be invited

Green Space

SAAP-I (1.00), SAAP-II (0.50) & SAAP-III (1.00)

2.50

1.50

10th SLTC meeting on 17.05.2017
NIT to be issued

Total

 

100.71

99.69

 

28

Udaipur

Sewerage

SAAP-II (85.00)Phase-I & SAAP-III (75.00) Phase-II

160.00

85.00+75.00=160.00

2nd SLTC  on 21.03.2016
LoA issued to  M/s GCC-NCCIPL (JV) vide no. 1188 dated 17.12.2016 amounting Rs. 72.26 (with Provisional Sum & without O&M and SBM).
Work order issued vide letter No.384 dated 17.01.2017 
Progress:-
Third Party Inspection for 10 Km pipes were completed. Procuring of pipes will be started shortly.
Physical Progress- 0%
 Financial Progress- 0.00  Crs)
& in 6th SLTC on 25.10.2016
NIT  issued on 16.02.2017 for Phase-II with Smart City,
 bid  opened on 27.03.2017, under evaluation.

Water Supply

SAAP-III

30.00

30.00

8th SLTC on 27.01.2017
Tender to be invited

Drainage

SAAP-II

11.50

11.50

2nd SLTC on 21.03.2016
LoA issued  to M/s Sandal Buildcon Pvt. Ltd vide no. 1197 dated 17.12.2016 amounting Rs. 11.74 (Without O&M)
Work order issued vide letter no. 383 dated 17.01.2017
Progress:-
Wall completed 100 mtr & Slab casting 50 mtr.
Physical Progress- 3.00%
 Financial Progress- 0.0 Crs

Green Space

SAAP-I (1.00) & SAAP-II (4.00)

5.00

5.00

2nd SLTC on 21.03.2016
NIT issued on 05.01.2017,
 bid opened on 16.02.2017, 3 bids received.
Financial bid opened on 08.03.2017 & evaluation is in progress.
Work order issued to M/s Ajnum Sekh (JV)
Work Order Amount- 3.03 Crs.

Total

 

206.50

206.50

 

29

Jhalawar

Water Supply

SAAP-III

75.00

75.23

5th SLTC  on 15.09.2016
Work Order issued to M/s Vishnu Prakash R. Pungaliya Ltd. vide no. 569-81 dated 18.04.2017 amounting Rs. 68.66 (Without O&M)
Physical Progress- 0.00%
Financial Progress- 0.00 Crs

Green Space

SAAP-II (0.50) & SAAP-III (2.00)

2.50

2.50

8th SLTC  on 27.01.2017
NIT issued on 15.05.2017.
Bid to be opened on 30.06.2017.

Total

 

77.50

77.73

 

Grand Total

 

3223.94

3087.79

 

 

Reform Incentive

1

Udaipur

City Bus, Big Bus Low Floor Buses (44 seater) = 10 Nos

6.54

Tender to be invited

Midi Bus, Low Floor (25 seater) Non A/C = 12 Nos

Midi Bus, Low Floor Hip-Hop services = 05 Nos

2

Ajmer

City Bus, Big Bus Low Floor Buses (44 seater) = 10 Nos

5.54

Tender to be invited

Midi Bus, Low Floor (25 seater) Non A/C = 12 Nos

3

Jodhpur

City Bus, Low Floor (25 seater) = 20 Nos

3.40

Tender to be invited

   

4

Jhalawar

NMT, Cycle Tracks & Bus Q shelter

5.32

NIT to be issued.

   

5

Sawai Madhopur

NMT, Cycle Tracks & Bus Q shelter

   

 

Total

20.80