RUIDP(Phase III)

Rajasthan Urban Investment Development Program (RUSDIP-RUIDP Phase-III)
As on 31.12.17
SN Package Name / ID Contract amount ( In Cr) Contract amount (witout O & m) expenditure( In Cr) St date of start/ Completion Water Supply Waste Water Management Drain
Water Tanks
(In nos)
Pipeline
(In Km)
Pumping Stations
(Nos)
Raw Water Reservoir (RWR) Water Treatment Plants
(Nos)
CWR
(Nos)
Electromagnetic Flow meter
(Nos)
Bulk Water Meters
(Nos)
House service connections
(Nos)
DMA (Nos) Sewer lines
 (In Km)
Sewage Treatment Plants
House sewer connections
(Nos)
Pumping Stations
(Nos)
(In Km)
(A) PROJECT LOAN TOWNS                               Nos Capacity      
1 Tonk                                        
  RUSDP/Tonk/01 Target  388 317.53 16.11.15 4 441 0   0   20 65 28280   250 2 20 22000 1  
  Achieve 37.43 37.43 24.11.18 80%,70%,30%,40% 103.26 0   0   0 2 2666   46.14 49% & 55 %     23.00%  
2 Pali                                        
  RUSDP/Pali/01 Target  496 414.99 02.11.15 0 664.29 0   0   18 49 49947 50 308.774 1 15 22000 2  
  Achieve 119.63 119.63 31.10.18 0 297 0   0   4 4 10630 1 153.48 61.28%     23% & 60 %  
  RUSDP/Pali/02 Target  84 71.05 11.07.16 7 41.13 4   1 1                    
  Achieve 16.73 16.73 10.07.18 55%,55%,47%,47%,55%,35%,47% 22.5     19% 5%                    
  Total Target  580 486.04   7 705.42 4   1 1 18 49 49947 50 308.774 1 15 22000 2  
  Total Achieve 136.36 136.36   50% 319.5 0   0.19 19 & 5 % 4 4 10630 1 153.48 61.28%   0 23 & 60 %  
3 Jhunjhunu                                        
  RUSDP/JJN/01 Target  237.5 207.83 09.01.17 1 562 6 0 0 500%     32650 38 127 1 7 9700 2  
  Achieve 23.52 23.52 29.03.19 0 70 0     0     1104   5.5 8%   0    
4 Sri gangangar                                        
  RUSDP/SGN/01 Target  555 473.39 06.01.17   415 2 2 1 4 41 40 50000 39 410     40925 1  
  Achieve 45.6 45.6 15.01.20   47.92 0 0 0 0 0 0 1842   35.58     0    
5 Bhilwara                                        
  RUSDP/BHL/01 Target  369.3 336.59 23.08.17                     416.6 1 30 43610 1  
    Achieve 0 0 22.08.20                     0 0   0 0  
6 Hanumnagarh                                        
    Target  281 244.76 27.10.17   510     1       40000   132 1 6 11135    
  Achieve 0 0 26.04.20   0     0                      
  Grand Total (Project loan) Target  2410.8 2066.14   12 2633.42 12   3 10 79 154 200877 127 1644.37 6 78 149370 7  
    Achieve 242.91 242.91   0 540.68 0   0.19 0 4 6 16242 1 240.7 0   0 0  
(B) PROGRAM LOAN TOWN                                        
1 Sawai Madhopur                                      
  RUSDP/Program Loan/ SWM/01 Target  112.62 103.04 15.06.17                     121 1 10 25000    
  Achieve 0.87 0.87 01.12.19                     4.3 0   0    
2 UDAIPUR                                      
  RUSDP/Program Loan/ Target  126.23 115 10.08.17                     68.5     8500   2.2
  Achieve 5.61 5.61 26.01.20                     0.4     0   0
3 BIKANER                                      
  RUSDP/Program Loan/ Target  187.35 171 26.07.17                     300 1 20 30000 1  
  Achieve 0 0 11.01.20                                
4 JHALAWAR-PATAN                                      
  RUSDP/Program Loan/ Target  143.72 129.18 26.08.17 4   2               149.5 2 9 17000 5  
  Achieve 6.19 6.19 25.02.20 0   0               0 0 0 0 0  
5 BANSWARA                                      
  RUSDP/Program Loan/ Target  14.45 14.45 19.09.17                               10
  Achieve 2.81 2.81 18.09.18                               0
6 KOTA                                      
  RUSDP/Program Loan/ Target  663.38 604                       396 2 55 20000 2  
  Achieve 0 0                       0 0   0    
7 MOUNT ABU                                      
  RUSDP/Program Loan/ Target  87.67 80                       55 5 7 4500 1  
  Achieve 0 0                       0 0   0    
  Grand Total (Program loan) Target  1335.42 1216.67                       1090 11 101 105000 9 12.2
  Achieve 15.48 15.48                       4.7 0   0 0 0
   Grand Total(A+B) Phase-III works Target  3746.22 3282.81   12 2633.42 12   3 10 79 154 200877 127 2734.37 17 179 254370 16 12.2
  Achieve 258.39 258.39   0 540.68 0   0.19 0 4 6 16242 1 245.4 0   0 0 0
  Other expenditure                                        
  (A) PMDSC expenditure   34.04                                  
  (B) Administrative increamental   14.2                                  
  Grand total expenditure   306.63                                  
 