S. No. Activities (as per Micro Action Plan) Micro Activities (as per Micro Action Plan) Estimate Cost (in Lakhs) Date of NIT Date of Work Order Physical Progress (in %) Financial Progress (in %) Likely Date of Completion Remarks     (If any)
1 Control of Air Pollution (15th Finance) Interlocking for dust suppression & greening of site 465 - - - - - Tender to be Floated 
Maintain potholes for dust free roads 250 - - - - - Tender to be Floated
Road Sweeping Machines  100 - - - - - Tender to be Floated 
Pollution Checking Machine for Vehicle in Garage 50 - - - - - Tender to be Floated 
Beautification work in Chambal Garden with Water sprinkler system 20 - - - - - Tender to be Floated 
Garden equipment 15 - - - - - Tender to be Floated 
Tree guard 100 - - - - - Tender to be Floated 
Electric Crematorium

150 - - - - - Tender to be Floated 
Jatting Machine 50 - - - - - Tender to be Floated 
Hand Cart, Bins 150 - - - - - Tender to be Floated 
    TOTAL 1350            
: :