Detail of under progress projects sanctioned by GOI under PMAY (U)
AHP Projects
S. No |
Name of City | ULB/ Development Authority /UIT | Name of Developer | Contact No. & Email | Sanctioned by GOI | Work start date | Work Completion date | Project Cost (Rs. in Lac) |
Sanctioned Flats | Houses taken up for construction | Completed | ||||
EWS | LIG | TOTAL | EWS | LIG | Total | ||||||||||
1 | Aanganwa, Jodhpur | Jodhpur Development Authority | M/s Nila Infrastructure, Ahamdabad | 7940036817 info[at]nilainfra[dot]com |
18.11.2015 | 17.02.2014 | 19.02.2018 | 5094.15 | 544 | 368 | 912 | 544 | 368 | 912 | 912 |
2 | Udaipur | UIT Udaipur | M/S Prime Civil Infrastructure (P) Ltd, JV K.K. Gupta Dholi magri, Bedwas Udaipur. | 0-22-28245635 contact[at]primecivil[dot]com |
18.11.2015 | 17.02.2014 | 09.04.2019 | 7676.63 | 848 | 584 | 1432 | 848 | 532 | 1380 | 1380 |
3 | Mohan Lal Sukhadiya, Kota | UIT Kota | M/s Navbharat Nirmaran company. Kota | 9829092058 ajaybakliwal52[at]gmail[dot]com |
18.11.2015 | 01.02.2015 | 31.07.2016 | 3034.80 | 368 | 96 | 464 | 368 | 96 | 464 | 464 |
4 | Chandra Sekhar Azad, Kota | UIT Kota | M/s Chelet Infra Technology | 9829062368 |
18.11.2015 | 02.07.2015 | 01.07.2018 | 4128.00 | 640 | 272 | 912 | 640 | 272 | 912 | 912 |
5 | Bhadana, Kota | UIT Kota | M/s Navbharat Nirmaran company. | 9829092058 ajaybakliwal52[at]gmail[dot]com |
18.11.2015 | 01.02.2015 | 31.07.2016 | 2710.80 | 252 | 288 | 540 | 252 | 288 | 540 | 540 |
6 | Ranpur, Kota | UIT Kota | M/s Navrbarat Nirmaran company. RANPUR SCHEME | 9829092058 ajaybakliwal52[at]gmail[dot]com |
18.11.2015 | 15.07.2015 | 14.01.2017 | 2784.00 | 320 | 256 | 576 | 320 | 256 | 576 | 576 |
7 | Balotra | ULB | M/s RDB Reality & Infrastructure Ltd, | 03344500500 info[at]rdbindia[dot]com |
18.11.2015 | 22.02.2016 | 21.02.2019 | 5119.75 | 592 | 384 | 976 | 400 | 128 | 528 | 528 |
8 | Balotra | ULB | M/s Prime Civil Infrastructure (P) Ltd, JV Nice Buildcon., | 0-22-28245635 contact[at]primecivil[dot]com |
18.11.2015 | 17.02.2014 | 30.04.2018 | 5058.31 | 608 | 416 | 1024 | 608 | 416 | 1024 | 1024 |
9 | Chittorgarh | ULB | M/s Hema Constructions, | 9414167619 hema_const[at]yahoo[dot]co[dot]in |
18.11.2015 | 01.05.2015 | 30.04.2018 | 5119.75 | 304 | 208 | 512 | 304 | 192 | 496 | 496 |
10 | Falna | ULB | M/s Prime Civil Infrastructure Ltd., Falna | 0-22-28245635 contact[at]primecivil[dot]com |
18.11.2015 | 15.07.2016 | 14.07.2019 | 6053.00 | 480 | 352 | 832 | 336 | 176 | 512 | |
11 | Kishangarh | ULB | M/s RDB Reality & Infrastructure Ltd, | 03344500500 info[at]rdbindia[dot]com |
18.11.2015 | 25.07.2017 | 14.07.2020 | 6557.25 | 714 | 519 | 1233 | 714 | 336 | 1050 | |
12 | Pushkar | ULB | M/s RDB Reality & Infrastructure Ltd | 03344500500 info[at]rdbindia[dot]com |
18.11.2015 | 01.01.2019 | 30.06.2022 | 2620.00 | 296 | 207 | 503 | 296 | 207 | 503 | |
13 | Nathdwara | ULB | M/s Hema Constructions, | hema_const[at]yahoo[dot]co[dot]in | 18.11.2015 | 01.05.2015 | 30.04.2017 | 2616.25 | 289 | 173 | 462 | 289 | 173 | 462 | |
14 | Sheoganj | ULB | M/s Sanchar Infratech Pvt. Ltd., Jaipur | sancharjaipur[at]yahoo[dot]com | 18.02.2016 | 02.12.2016 | 01.06.2020 | 2732.80 | 256 | 192 | 448 | 256 | 192 | 448 | |
15 | Bhilwara | UIT Bhilwara | M/s Nila Infrastructures Ltd. | 7940036817 info[at]nilainfra[dot]com |
18.02.2016 | 02.06.2016 | 31.03.2020 | 5168.66 | 604 | 288 | 892 | 604 | 288 | 892 | |
16 | Dungarpur | ULB | M/s Prime Civil Infra, Mumbai | 0-22-28245635 contact[at]primecivil[dot]com |
18.02.2016 | 19.03.2016 | 31.03.2019 | 1326.00 | 272 | 88 | 360 | 272 | 88 | 360 | |
17 | Beawer | ULB | M/s Sanchar Infratech Pvt. Ltd., Jaipur | sancharjaipur[at]yahoo[dot]com | 30.10.2017 | 14.11.2017 | 13.05.2021 | 5515.20 | 848 | 368 | 1216 | 656 | 172 | 828 | |
18 | Jhalawar | ULB | M/s National Co-operative Consumer's Federation of India Ltd. (NCCF) | 9669269455 nccf[dot]jaipur141[at]gmail[dot]com |
18.02.2016 | 04.01.2017 | 03.01.2020 | 9415.35 | 744 | 712 | 1456 | 744 | 530 | 1274 | |
19 | Kota | UIT Kota | M/s Pawan Kumar Jain, Kota | 9414177928 email id not available |
31.08.2016 | 13.08.2016 | 12.05.2018 | 3593.70 | 532 | 160 | 692 | 532 | 160 | 692 | |
20 | Kota | UIT Kota | M/s SR Enterprises, Kota | 9414179163 email id not available |
31.08.2016 | 13.08.2016 | 12.11.2017 | 1738.80 | 368 | 0 | 368 | 368 | 0 | 368 | |
21 | R-1 to R-4 , South Extension, Udaipur | UIT Udaipur | M/s Nila Infrastructure, Ahamdabad | 7940036817 info[at]nilainfra[dot]com |
22.11.2016 | 30.06.2016 | 29.06.2019 | 6480.00 | 640 | 512 | 1152 | 640 | 512 | 1152 | |
22 | Tanwara, Ph-I, Jodhpur | Jodhpur development Authority | M/s Prime Civil Infra, Mumbai | 0-22-28245635 contact[at]primecivil[dot]com |
22.11.2016 | 04.07.2016 | 03.07.2019 | 2970.00 | 400 | 160 | 560 | 400 | 160 | 560 | |
23 | Chokha, Jodhpur | Jodhpur development Authority | M/s Vadera Tradelink Pvt. Ltd., Jodhpur | 9414671658 goutamj[at]yahoo[dot]com |
29.05.2017 | 20.04.2017 | 19.04.2021 | 3925.84 | 464 | 320 | 784 | 464 | 320 | 784 | |
24 | Lordi Pandit, PKG-8, Jodhpur | Jodhpur development Authority | M/s Vadera Tradelink Pvt. Ltd., Jodhpur | 9414671658 goutamj[at]yahoo[dot]com |
29.05.2017 | 20.04.2017 | 19.04.2021 | 6808.63 | 896 | 496 | 1392 | 896 | 496 | 1392 | |
25 | Lordi Pandit, PKG-9, Jodhpur | Jodhpur development Authority | M/s Vadera Tradelink Pvt. Ltd., Jodhpur | 9414671658 goutamj[at]yahoo[dot]com |
29.05.2017 | 20.04.2017 | 19.04.2021 | 7669.50 | 1008 | 560 | 1568 | 1008 | 0 | 1008 | |
26 | Lordi Pandit, PKG-10, Jodhpur | Jodhpur development Authority | M/s Vadera Tradelink Pvt. Ltd., Jodhpur | 9414671658 goutamj[at]yahoo[dot]com |
29.05.2017 | 20.04.2017 | 19.04.2021 | 7583.06 | 912 | 608 | 1520 | 912 | 0 | 912 | |
27 | Lordi Pandit, PKG-11, Jodhpur | Jodhpur development Authority | M/s Vadera Tradelink Pvt. Ltd., Jodhpur | 9414671658 goutamj[at]yahoo[dot]com |
29.05.2017 | 20.04.2017 | 19.04.2021 | 8217.32 | 1008 | 672 | 1680 | 1008 | 672 | 1680 | |
28 | Barli, Jodhpur | Jodhpur Development Authority | M/s Nila Infrastructure, Ahamdabad | 7940036817 info[at]nilainfra[dot]com |
30.10.2017 | 15.01.2018 | 14.02.2022 | 14443.20 | 2128 | 1024 | 3152 | 724 | 0 | 724 | |
29 | SPM Yojana, Bharatpur | UIT Bharatpur | M/s Katira Construction, Ahamdabad | 9825225068 kclbharatpur[at]gmail[dot]com |
29.05.2017 | 07.06.2017 | 16.12.2019 | 1587.00 | 320 | 0 | 320 | 320 | 0 | 320 | |
30 | Sirohi | ULB | M/s Sanchar Infratech Pvt. Ltd., Jaipur | sancharjaipur[at]yahoo[dot]com | 29.05.2017 | 06.12.2016 | 05.12.2020 | 2005.00 | 400 | 96 | 496 | 400 | 96 | 496 | |
31 | Hindon City | ULB | M/s Shilpa Constrcution, Jaipur | 9414045162 shilpa.cons26[at]yahoo[dot]in |
29.05.2017 | 04.01.2017 | 04.01.2020 | 3492.97 | 544 | 272 | 816 | 544 | 115 | 659 | |
32 | Tanwara, Ph-II, Jodhpur | Jodhpur Development Authority | M/s Prime Civil Infra, Mumbai | 0-22-28245635 contact[at]primecivil[dot]com |
30.10.2017 | 12.10.2017 | 11.10.2021 | 3916.80 | 512 | 320 | 832 | 512 | 320 | 832 | |
33 | Rajsamnd | ULB | M/s National Co-operative Consumer's Federation of India Ltd. (NCCF) | 9669269455 nccf[dot]jaipur141[at]gmail[dot]com |
30.10.2017 | 01.09.2017 | 03.01.2020 | 5155.20 | 608 | 464 | 1072 | 608 | 334 | 942 | |
34 | Pali | ULB | M/s National Co-operative Consumer's Federation of India Ltd. (NCCF) | 9669269455 nccf[dot]jaipur141[at]gmail[dot]com |
30.10.2017 | 04.01.2016 | 04.01.2019 | 4891.20 | 688 | 368 | 1056 | 688 | 368 | 1056 | |
35 | Nimbahera | ULB | M/s Ashahi Infra & Projects (Mumbai) JV with M/s Mahalaxmi Enterprises (Nimbahera) | 09672976793 asahimum[at]gmail[dot]com |
30.10.2017 | 16.08.2017 | 15.08.2021 | 5812.80 | 752 | 480 | 1232 | 752 | 475 | 1227 | |
36 | R-5, South Exten. Udaipur (UIT) | UIT Udaipur | M/s Rythum Infra Structure, Ahamdabad | (0) 079-26463196 rhythm[at]rhythmconstruction[dot]co[dot]in |
26.03.2018 | 15.03.2017 | 14.09.2020 | 3186.00 | 448 | 128 | 576 | 448 | 128 | 576 | |
37 | Khetri | ULB | M/s Nirwan Construction Company, Khetri | 9829072601 hr[dot]gwala[at]gmail[dot]com |
26.03.2018 | 28.11.2016 | 27.11.2020 | 3633.00 | 416 | 224 | 640 | 416 | 224 | 640 | |
38 | SPZ Yojna, Bhartpur (UIT) | UIT | M/s Rajendra Singh Bhamu, Jaipur | 9829057499 rajendrabhamboo[at]yahoo[dot]co[dot]in |
26.03.2018 | 10.11.2017 | 19.05.2020 | 1863.00 | 208 | 96 | 304 | 208 | 96 | 304 | |
39 | Bundi | ULB | M/s National Co-operative Consumer's Federation of India Ltd. (NCCF) | 9669269455 nccf[dot]jaipur141[at]gmail[dot]com |
26.03.2018 | 01.01.2018 | 31.12.2022 | 5045.00 | 720 | 384 | 1104 | 646 | 354 | 1000 | |
40 | Raipura, Kota (UIT) | UIT Kota | M/s BCC Developers & Promoters , Kota | 011-41433619 anilpawan[at]icai[dot]org |
26.03.2018 | 27.102.2017 | 26.04.2019 | 2560.00 | 288 | 112 | 400 | 288 | 112 | 400 | |
41 | Bikaner | UIT Kota | M/s Rythum Infra Structure, Ahamdabad | (0) 079-26463196 rhythm[at]rhythmconstruction[dot]co[dot]in |
26.03.2018 | 21.03.2018 | 20.09.2020 | 8315.00 | 456 | 608 | 1064 | 456 | 608 | 1064 | |
42 | Dangiyon ki pancholi, Udaipur | UIT Udaipur | M/s Gyarshi lal Mohan | Not available | 25.06.2018 | 12.03.2018 | 11.08.2020 | 5543.33 | 304 | 0 | 304 | 304 | 0 | 304 | |
43 | Dagla Ka Kheda, Chittorgarh | UIT Chittorgarh | M/s Navbharat Norman Company JV with M/s Ankita Constrcution, Kota | 9829092058 ajaybakliwal52[at]gmail[dot]com |
22.11.2016 | 16.01.2019 | 15.01.2022 | 2430.00 | 240 | 192 | 432 | 240 | 192 | 432 | |
44 | Kheshavraipatan | ULB | M/s National Co-operative Consumer's Federation of India Ltd. (NCCF) | 9669269455 nccf[dot]jaipur141[at]gmail[dot]com |
18.02.2016 | 29.11.2017 | 28.11.2021 | 9666.92 | 760 | 752 | 1512 | 418 | 361 | 779 | |
45 | Choti Sadri | ULB | M/s Dullar Real Estate Pvt. Ltd., Jaipur | 9001001649 dullarbrothers[at]gmail[dot]com |
26.03.2018 | 11.06.2018 | 10.12.2020 | 1567.00 | 288 | 0 | 288 | 288 | 0 | 288 | |
46 | Dangioy ki Pancholi, Udaipur | UIT | M/s Rythum Infra Structure, Ahamdabad | (0) 079-26463196 rhythm[at]rhythmconstruction[dot]co[dot]in |
25.02.2019 | 6220.47 | 632 | 352 | 984 | 632 | 352 | 984 | |||
TOTAL-A | 223051.44 | 25919 | 15131 | 41050 | 23571 | 11165 | 34736 | 6832 |
BLC Projects
S. No |
Name of City | ULB/ Development Authority /UIT | Name of Developer | Contact No. & Email | Sanctioned by GOI | Work start date | Work Completion date | Project Cost (Rs. in Lac) |
Sanctioned Flats | Houses taken up for construction | Completed | ||||
EWS | LIG | TOTAL | EWS | LIG | Total | ||||||||||
1 | Bhilwara | UIT | Beneficiary self | - | 22.11.2016 | 784.8 | 180 | 0 | 180 | 110 | 0 | 110 | 18 | ||
2 | Todaraisingh | ULB | Beneficiary self | - | 25.06.2018 | 684.52 | 157 | 0 | 157 | 61 | 0 | 61 | 0 | ||
TOTAL-B | 1469.32 | 337 | 0 | 337 | 171 | 0 | 171 | 18 | |||||||
G.TOTAL (A+B) | 224520.76 | 26256 | 15131 | 41387 | 23742 | 11165 | 34907 | 6850 |