SEWERAGE IN ELEVEN CITIES(UIDSSMT)
Sewerage Projects in 11 cities sanctioned under UIDSSMT transition phase
1.) Sewerage Work- 11 Cities (Chirawa, Laxmangarh,Jaitaran,Nimbaheda,Bhadra,Nawalgarh,Suratgarh,Bari-Sadri,Fatehnagar Sanwad,Kushalgarh and Ramgarh Shekhawati).
2.) Sanctioned Amount: Rs. 657.14 cr
3.) Fund Share-GoI- 60%, GoR- 20% and ULB's - 20%.
4.) Work Completed- 5 cities(Chirawa,Bari-Sadri,Fatehnagar Sanwad,Kushalgarh and Jaitaran)
5.) Work in Progress- 6 cities (Laxmangarh,Nimbaheda,Bhadra,Nawalgarh,Suratgarh and Ramgarh Shekhawati).
6.) Total Sewer Line- 798 km, Completed- 744 km.
7.) Total Sewerage Treatment Plant - 22 , Completed- 13, WIP- 9.
8.) Total Sewer Connection- 45000, Completed- 30649.
9.) Physical Progress- 90%
10.) Financial Progress- 80% (Rs. 504.65 cr).
11.) Detail of amount received from finance department:-
- Year 2013-14 : Rs. 213.01 cr.
- Year 2014-15 : Rs. 86.25 cr.
- Year 2015-16 : Rs. 46.13 cr.
- Year 2016-17 : Rs. 66.52 cr.
- Year 2017-18 : Rs. 57.03 cr.
- Year 2018-19 : Rs. 4.48 cr.
- Year 2019-20 : Rs. 24.52 cr.
- Year 2020-21 : Rs. 0.32cr.
12.)All work likely to be completed upto June,2021.