·               59 ROBs/RUBs have been taken up in urban area in last 7 years with project cost of Rs. 1745.56 Cr. (State share is Rs. 1065.81 Cr. and Railway share is Rs. 679.75 Cr.)

·               Out of 59, 37 ROBs/RUBs have been completed till date. (24 ROBs and 13 RUBs)

·               10 ROBs/RUBs are under progress. (9 ROBs and 1 RUBs)

·               12 ROBs/RUBs yet to be started.(6 ROBs and 6 RUBs)

·               3 ROBs declared in budget 2019-20, have recently approved in RTIDF meeting dated 22.10.2019 subject to the condition that Railway will contribute their share.

 

 

 

 

: :