Daily Projcet Report
Work In Progress
o Construction & Improvement of Ravindra Rangmanch
Cost: - 950.00 Lacs
August-15 to June-16
o Construction of Heritage Walk Work from Kotegate to Bikaji Tekari via City kotwali, Rampuria Haveli, Aadinath Mandir, Laxmiknath Mandir.
Road Work: - 80.00 Lacd
Interlocking Tile Work: - 75.00 Lacs
Drain Work: - 25.00 Lacs
Electrical: - 65.00 Lacs
Total: - 245.00 Lacs
Work Start: - August – 2015
Work in Progress
o Beautification Work in Sursagar
Cost: - 147.00 Lacs
November-15 to September-16