Completed Project 32
Construction And Development Of Driving Track At Bhuwana | ||
---|---|---|
1 | W/O Amount | 36.98 Lacs |
2 | Date Of Commencement | 23-12-2014 |
3 | Date of Completion | 15-02-2016 |
4 | Description | This work is done for R.T.O. department by UIT Udaipur under deposit scheme at Chitrakut Nagar. A track to test the driving capabilities of a driver has been made and various road sign boards have been placed to test the knowledge of a driver. |