Widening of Road at Hiran Magri Sector 9-14 Link Road.
1 W/O Amount  46.16 Lacs    
2 Length 850.00 Mtr    
3 Date Of Commencement 02-09-2015    
4 Date of Completion 01-03-2016    
5 Description Re-strengthen of Master Plan road at Hiran Magri Sector 9-14 link road is under progress. It is a 4- Lane road. Easy approach to Goverdhan Vilas and N.H.-8 By-Pass and also connect UIT Scheme Sec. 9, Sec 12 to Sec. 14.
   